October 2009

Property acquisition begins

 

July 2008

Consultants for the city present 3 possible layouts for the Main Library

 

February, 2008

The Baker St. Parking lot has been selected as the preferred site for the new library. The Economic Development

department is working on an integrated plan to develop the complete site and will be reporting back in mid summer.

Construction might begin in 2009

 

February, 2009

The Library will front on Wyndham St. and property will be expropriated