December 2008
Park design in progress with two public meeting held. Construction to
begin next year
East End Trail reaching Eastview Rd.
October 2007
The first half of the East end Trail network is completed, construction
on the second half will begin in 2008
October 2008
The bridge was installed over Hadati Creek just east of Summit View
Drive
April 2009
The board walk over Hadati Wetland was completed and the trail
connection from
Grange and Watson is under construction.
$870,000 of funding for East End trails has be approved in 2007
Construction will begin in the spring of this year
This is the current building plan